Saturday, October 30, 2010

Day 104 - Update - Saturday 30 October 2010

It's been a few weeks since my last update and this is what has been done:

*Electricals

*AirConditioning

*Front render feature finished

*Lower roof (alfresco) tiling almost done

*Front and back cladding being finished today


The gyprock and insulation are being delivered on Monday so hopefully we'll see a start on the inside early next week!

Saturday, October 9, 2010

Day 82 - Nice Clean Bricks!- Friday 8 October 2010

There has been a little bit of a delay due to the rain but nothing major.  The bricking is finished and today they were cleaned.   According to our SS the eaves are being put up tomorrow, and next week will see them painted, the downpipes installed and also hopefully the rendering at the front done.