Friday, September 3, 2010

Day 47 - Weekly Update from Site Supervisor.

Received our weekly update from our SS today.  He advised that the sand and all other stuff needed for the brick laying is being delivered on Monday and that the brickies are due to start on Tuesday!

Once the bottom level has been bricked the scaffolding will be put up, then the roof tiles and the top floor bricks get done.

Next week we'll also have access "upstairs" finally so I'll have lots of new photos in the next update!